Closures Updates
12/2/2024 - Main pool is completely drained.

12/5/2024 - Preserving the racing lanes and target cut-outs is underway.

12/12/2024 - Demolition of pool interior is complete.


12/17/2024 - Pool Deck is being grinded. Removal and replacement of pool lights is underway.


12/18/2024 - Pool Deck is currently being patched.


12/20/2024 - Pool deck is going through its first coat of paint.


1/3/2025 - New pool deck markers have been added. 
1/8/2025 - The water line tile is being removed and will be replaced with new tile.
1/31/2025 - The water line tile has been completely replaced.
2/12/2025 - The pool is currently being plastered and completed within the same day. The pool will also be filled the same day. 